Sewing Production Calculator

Estimate output capacity from available operator minutes and standard minute value.

About the Sewing Production Calculator

Convert available labor minutes into a simplified capacity estimate.

How to use it

  1. Enter the number of operators and daily hours.
  2. Enter the garment SMV and expected efficiency.
  3. Calculate estimated output per day and hour.

Formula

Daily output equals operators times hours times 60, multiplied by efficiency, then divided by SMV.

Example

Twenty operators working eight hours at 80% efficiency on a 15-minute garment estimate about 512 garments per day.

Notes

This planning ratio does not model line balance, changeovers, absenteeism, learning curves or quality losses.